.TRS_Editor P{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor DIV{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor TD{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor TH{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor SPAN{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor FONT{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor UL{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor LI{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor A{line-height:2;font-family:宋體;font-size:12pt;}
.TRS_Editor P{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor DIV{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor TD{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor TH{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor SPAN{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor FONT{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor UL{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor LI{line-height:2;font-family:宋體;font-size:12pt;}.TRS_Editor A{line-height:2;font-family:宋體;font-size:12pt;}
國內(nèi)最重轉(zhuǎn)體橋首個節(jié)段順利澆筑
長江日報融媒體4月16日訊(記者王謙 通訊員車春蘭)武漢北四環(huán)建設又有新進展。4月16日,由中鐵七局施工的北四環(huán)跨鐵工程轉(zhuǎn)體橋首塊混凝土節(jié)段順利澆筑,開啟橋梁上部結(jié)構施工。
該轉(zhuǎn)體橋重3.3萬噸,是國內(nèi)最重最寬的轉(zhuǎn)體橋。北四環(huán)線項目與鐵路交叉,上跨八條既有鐵路線,共要建4個跨鐵路的轉(zhuǎn)體橋,是北四環(huán)項目控制性工程。
中鐵七局北四環(huán)項目部總工程師華志鴻介紹,工程分別上跨京廣貨線上下行、武北漢丹出發(fā)線和到達線、京廣客線上下行、武漢北下行環(huán)發(fā)線、灄口貨場專用線等8條鐵路。新建橋梁全長1.15公里,其中,4個墩連續(xù)梁均采用轉(zhuǎn)體施工。
國內(nèi)最重轉(zhuǎn)體橋首個節(jié)段順利澆筑
長江日報記者在現(xiàn)場看到,距離地面約20米處,20多位工人正在搭建好的轉(zhuǎn)體主墩上進行箱梁的澆筑,兩臺混凝土天泵不停地作業(yè)。
“4個轉(zhuǎn)體橋總重量11.5萬噸,其中2個各重達3.3萬噸,是國內(nèi)最重最寬的轉(zhuǎn)體橋。此次澆筑的2號墩轉(zhuǎn)體橋是最重之一,長142米,寬43米,由7塊混凝土節(jié)段組成,今天澆筑的是首個節(jié)段?!比A志鴻說,混凝土澆筑量2289立方米,相當于三層樓高兩個籃球場大,預計要澆筑24小時,到17日早上完成。
北四環(huán)轉(zhuǎn)體橋首塊混凝土節(jié)段順利澆筑,標志四環(huán)線北段與鐵路交叉工程上部結(jié)構施工邁出了重要一步,為后續(xù)施工各節(jié)點完成及轉(zhuǎn)體施工打下堅實基礎。據(jù)悉,9月30日之前,4個轉(zhuǎn)體橋的轉(zhuǎn)體施工將要全部完成。